GH-PPA-DRAFT-05
Ghana-Togo/Benin Border Towns Cross-Border Electricity Supply Project
Electricity Company of Ghana (ECG) · Other · 2.00 MW · Ghana–Togo border interconnection, Volta Region, Ghana
GH-PPA-DRAFT-05
Ghana-Togo/Benin Border Towns Cross-Border Electricity Supply Project
Electricity Company of Ghana (ECG) · Other · 2.00 MW · Ghana–Togo border interconnection, Volta Region, Ghana
Summary
A cross-border bulk electricity sale from ECG to Communauté Électrique du Bénin (CEB), supplying five delivery points in the Volta Region at a contracted 2 MW, under a 5-year agreement signed 19 August 2011. The energy charge is a flat PURC-approved tariff of 20.0 US cents/kWh plus a flat monthly service charge per delivery point; no capacity-charge rate or take-or-pay obligation is specified in the agreement. Note: ECG is the seller in this contract, not the offtaker, unlike the other 12.
Key terms
- Offtaker
- Communauté Électrique du Bénin (CEB)
- Signing date
- 2011-08-19
- Financial close
- —
- Commercial operation
- 2010-10-28
- Contract end
- 2016-08-19
- Contract duration
- 5 years
- Contract status
- Active
- Tariff structure
- Capacity + Energy
- Capacity charge
- —
- Energy charge
- —
- Key risk features
- None listed
- Indexation formula
- No automatic escalation formula in the tariff. The stated energy rate (20.0 US cents/kWh) is pegged to the PURC SLT-HV tariff 'as at June 2010'; clause 11.6 allows Seller-initiated rate change proposals for cost reasons, periodic re-review in line with PURC's own tariff reviews, and mandatory review if demand exceeds 2,500 kW.