Tropical Energy Resources 30-50 MW Renewable Energy Facility, Tema

Tropical Energy Resources Ltd · Other · 50.00 MW · Near ECG's Dawhenya Primary Substation, Tema, Ghana

Summary

A 30-50 MW renewable energy facility near ECG's Dawhenya substation in Tema, phased in over its first months of operation, supplying ECG under a 15-year energy-only PPA signed 27 November 2007 (reviewed/renewed every 5 years). The energy charge is 7.0 US cents/kWh or the PURC Bulk Generation Tariff if higher, capped at 10 US cents/kWh for the first 10 years, with under-consumption/under-supply penalty adjustments and a take-or-pay obligation.

Key terms

Offtaker
Electricity Company of Ghana (ECG)
Signing date
2007-11-27
Financial close
—
Commercial operation
—
Contract end
2022-11-27
Contract duration
15 years
Contract status
Active
Tariff structure
Energy-only
Capacity charge
—
Energy charge
USD 7.0000/kWh
Key risk features
Take-or-pay
Indexation formula
Flat USD rate of 7.0 US cents/kWh (or the PURC Bulk Generation Tariff if higher), capped at 10 US cents/kWh, for the first 10 years; renegotiated with PURC and ECG thereafter, with no stated floor. Paid in USD or its cedi equivalent at the prevailing Interbank rate; no hedging mechanism.